Mogalakwena PV Public Participation

Invitation to participate


Notice of application for:

AN AMENDMENT TO THE ENVIRONMENTAL AUTHORISATION OF THE MOGALAKWENA PHOTOVOLTAIC SOLAR ENERGY FACILITY FOR THE MOGALAKWENA MINE WITHIN THE MOGALAKWENA LOCAL MUNICIPALITY, LIMPOPO PROVINCE

Mogalakwena Mine Solar Power (Pty) Ltd was granted an Environmental Authorisation (EA) to construct a photovoltaic (PV) solar energy facility and associated transmission lines to supply power to the mine. The EA was granted on 9 December 2021 (ref. no. 12/1/9/2/-W89).

Due to project changes, the scope of the EA will now have to be amended.

Zutari (Pty) Ltd was appointed as the independent Environmental Assessment Practitioner to undertake a Substantive (Part 2) Amendment for the proposed change in EA scope, in accordance with Chapter 5 of the Environmental Impact Assessment (EIA) Regulations Government Notice (GN) R982 of 2014.

Mogalakwena Mine Solar Power appointed Pele Green Energy (PGE) and EDF Renewables, a consortium known as PGE-EDFR as the Independent Power Producer to develop the proposed project. PGE provided a design for the project, but the approved footprint proved insufficient. The only available area for expansion on the site is a Critical Biodiversity Area (CBA) east of the authorised layout. The proposed expansion area is approximately 24.9 ha, of which approximately 16 ha is within an area designated as a CBA 1 in the Limpopo Conservation Plan (C-Plan).

Condition 4 of the existing EA excludes the CBA from the development footprint. Therefore, an amendment to the EA is required from the competent authority, Limpopo Department of Economic Development, Environment and Tourism (LEDET) to authorise development in this proposed area of expansion.

This application applies for authorisation of expansion of the approved footprint, which includes the solar farm, inverters, internal access roads for servicing and maintenance of the site; stormwater management infrastructure; and temporary equipment laydown areas/construction camps. This will allow up to 120 MW of total generation capacity of the plant as authorised by the existing EA.

Other components of the project that have already been authorised remain unchanged. This includes electricity generation of up to 120MW, connection and control buildings, a guard cabin; weather stations; perimeter fencing; and a substation and/or switchyard to convert power for transmission to Mogalakwena Mine.

The PV energy facility and associated infrastructure are proposed to be developed on the preferred site situated on the Remainder of Portion 3 of the Farm Armoede 823. The proposed site is located east of the N11 main road, 27 km northwest of the town of Mokopane in the Limpopo Province.

Part 2 Amendment Report Final

Amendment Report

APPENDIX A: Environmental Authorisation (EA)

Environmental Authorisation

APPENDIX B: Authority communications

Mogalakwena Solar PV meeting presentation: 4 November 2022

Mogalakwena Solar PV meeting presentation: 2 August 2022

Mogalakwena Solar PV meeting presentation: 30 September2022

SIP Declaration 20c

APPENDIX C: Maps and drawings

General layout

Location

Project Footprint

Proposed layout

Regional locality

Amended layout map

Habitat unit

Sensitivity AviFauna

Sensitivity Fauna

Sensitivity Flora

Topo map

APPENDIX D: Specialist assessments

Heritage Impact Assessment

Avifaunal Assessment

Biodiversity Impact Assessment -Part A

Biodiversity Impact Assessment -Part B (Floral Assessment)

Biodiversity Impact Assessment -Part C (Faunal Assessment)

Noise Compliance Statement

Noise Specialist Declaration

Freshwater Ecosystems and Aquatic Impact Report

Freshwater Ecosystems and Aquatic Impact WULA Memo

Agricultural Compliance Statement

Landscape and Visual Impact Confirmation Report

Landscape and Visual Impact Declaration

Social Impact Assessment – LEDET Specialist Declaration

Facility SIA

Paleonthology Impact Report

Archival Heritage Report

APPENDIX E: Public participation process

I&AP Database

Notification Letter

Newspaper Ad Proof

Site Notice

Background Information

Comment and Response Report

Proof of Site Notice placement | Image 1

| Image 2 | Image 3 | Image 4 | Image 5 | Image 6 | Image 7  | Image 8  | Image 9  | Image 10  | Image 11  | Image 12  | Image 13

Public Participation Invitations | Mapela Tribal Council

Public Participation Invitations | Molekana Village

Public Participation Invitations | Rooibokfontein Village

Public Participation Invitations | Sekhaolele – Armoede Village

Public Participation Meetings Attendance Register | Ga Molekana

Public Participation Meetings Attendance Register | Mapela Tribal Council

Public Participation Meetings Attendance Register | Rooibokfontein Village

REGISTRATION AND COMMENTS:

contact-us