FINAL BASIC ASSESSMENT REPORT: MACASSAR WASTEWATER TREATMENT WORKS, CAPACITY EXTENSION AND ASSOCIATED INFRASTRUCTURE REFURBISHMENT, WESTERN CAPE

Macassar Wastewater Treatment Works, Capacity Extension and Associated Infrastructure Refurbishment, City of Cape Town, Western Cape

Project Proposal:

On the 07 July 2016, the Department of Environmental Affairs and Development Planning issued an Environmental Authorisation (EA) 16/3/1/1/A3/39/2078/14 to the City of Cape Town approving the proposed upgrade and expansion of the Macassar Wastewater Treatment Works (WWTW) and associated infrastructure. However, due to the time that has passed since the approval in 2016, new design engineers have been appointed to finalise the detailed design. The design engineers have identified alternative technology options that will enable the works to run more efficiently and improve the quality of the effluent being discharged to the estuary.

The proposed revision to the design upgrades will require the clearance of more than 1ha of indigenous vegetation, which includes Endangered Cape Flats Dune Strandveld vegetation. Therefore, Listing Notice 1, Activity 27 and Listing Notice 3 Activity 12 is being applied for.

Legal Framework:

To seek environmental authorisation, a Basic Assessment Reporting (BAR) process for the proposed works is required in terms of the National Environment Management Act (NEMA, Act No. 107 of 1998, as amended) and the 2014 Environmental Impact Assessment (EIA) Regulations (as amended). An Application for Environmental Authorisation (EA) has been submitted to the Western Cape Department of Environmental Affairs and Development Planning (DEA&DP).

DEA&DP Ref Number: 16/3/3/1/A3/39/2054/24

Available Information:

Final BAR and Comments and Response Report. (CRR)

Contact Person:Corlie SteynEmail:PPP@zutari.com
Telephone:044 805 5400Postal:PO Box 509, George, 6530
Fax:044 873 5843  
Disclaimer: Zutari places a high premium on the privacy & personal information of our stakeholders. Please note that, as a Registered I&AP in terms of the Environmental Impact Assessment (EIA) Regulations, 2014, your personal details including your name, contact details and address is recorded into a register. The processing of personal information is subject to the Protection of Personal Information Act (POPIA), Act No. 4 of 2013, which came into effect on the 1st of July 2021.

Basic Assessment Report (Final BAR)

Basic Assessment Report (Final BAR)

Appendix A: Maps

Appendix A1.1: Locality map

Appendix A2: Coastal zones

Appendix A2.1: Coastal zones

Appendix A3: Map with the GPS co-ordinates for linear activities

A3.1 GPS Co-ordinates

A3.2 Co-ordinates every 100m

Appendix B: Plans

Appendix B1 | Site Development Plan

B1:1 Engineer Site Plan 1 of 2
B1:2 Engineer Site Plan 2 of 2
B1.3 Property Boundaries
B1.3 Site establishment and stockpile area
B1.4 Roads and Servitudes
B1.5 Environmental Sensitivities
B1.6.1 Flood lines
B1.6.2 Floodlines 1 3000
B1.7 Contours

Appendix B2 | A map of appropriate scale, which superimposes the proposed development and its associated structures and infrastructure on the environmental sensitivities of the preferred site, indicating any areas that should be avoided, including buffer areas.

B2.0 Sensitivity maps
B2:1a Biodiversity map 1:25,000
B2:1b Biodiversity sensitivity map 1:7,000
B2:1c Biodiversity and Freshwater 32m buffer map
B2.2 Freshwater sensitivity map 1:12,000
B2.3 Heritage & Palaeo sensitivity map 1:12,000
B2.4 Combined sensitivity map 1:12,000
B2.5 CBA Protected area
B2.6 All sensitivities and buffers map 1;20,000

Appendix C: Photographs

Photographs

C1: Photographs – Dated April 2022
C2: Map with vantage points
C3 Photographs matching vantage points

Appendix D: Biodiversity overlay map

Overlay map

D1: Biodiversity sensitivity map
D.2 Biodiversity map – zoomed

 

Appendix E: Permit(s) / license(s) / exemption notice, agreements, comments from State Department/Organs of state and service letters from the municipality.

E.0: Permits

E1: Final comment/ROD from HWC

E1.1: Section 38 Response to NID
E1.2: Response from Stephanie Barnardt from HWC
E1.3: HWC Consultation Letter
E1.4: FC Dec 2024

E2: Comment & Feedback: Ismat Adams

E3.1: Email WUL Amend to DWS
E3.2: Amendment template
E3.3: Proof to DWS
E3.4:DWS

E4: Comments on BAR

E10: Effort to Contact
E11: Pollution
E13: Air
E14: DEADP
E15: Erf

E15.1: Final comment from CCR Biodiversity

E16: Confirmation of services (water, electricity, sewage, solid waste management)

E20: Proof of agreement/TOR of the specialist studies conducted. – Refer also to the section in each Specialist Study pertaining to the TOR

E20.1: Sub-consultant agreement – Heritage
E20.2: Sub-consultant agreement – Freshwater & Botanical
E20.3: Sub-consultant agreement – Agricultural
E20.4: Sub-consultant agreement – Terrestrial
E20.5: Sub-consultant agreement – Biodiversity offset

E21: Proof of land use rights

E21.1: Landuse ERF703 Re
E21.2: Landuse ERF1205
E21.3: Zoning Map
E21.4: Zoning map including cable

Appendix F: Public participation information

F.0: PPP

F0.1 Macassar PPP Report – Second round

F1: Meeting record
F2: Notifications

F2.1 Email notifications
F2.1.1 Proof of Postage
F2.2 Reminder email
F2.3 Proof of postage – Second round
F2.4 Email notifications – Second round
F2.5 Reminder email – Second round

F3.1 Proof of advert
F3.2 Proof of advert 2
F3.3 Proof of advert 3
F3.4 Advert – Second round
F4.1 Signed Transmittal
F4.2 Signed Transmittal – Second PPP
F4.3 Transmittal – Second round

F5 Offset Site Visit Register
F6: Proof of Advert – Public meeting
F7.1: Presentation
F7.2: Meeting Register
F7.3: Engagement meeting Second round
F7.4: Register – Public meeting
F.8 Final Comments and Responses Report
F9: Final I&AP Database

Appendix G: Specialist reports

G.0 Specialists
G.1 Agricultural Compliance Statement
G.2 Terrestrial Biodiversity Assessment
G.3 Heritage Impact Assessment

G3.1: Heritage Impact Assessment
G3.2: Paleontology Assessment
G3.3: Response to Notice of Intent

G.4 Freshwater Impact Assessment
G.5 Ecological Impact Assessment
G.6 Geotechnical Report
G.7 Defence Compliance Statement
G8.1 Biodiversity Offset Memo
G8.2 Macassar WWTW Biodoversity Offset Memo
G8.3 Biodiversity Offset Strategy
G8.4 Biodiversity Offset Agreement
G8.5 Draft offset Report
G8.6 Biodiversity Offset Report
G8.7 Email CCT Biodversity Comments incorporated
G8.8 Offset BMB Letter

Appendix H: EMPr

H.0: Macassar Water Treatment Works Environmental Management Plan
H.1 EMPr Final

H1.1 App C No-Go Zones
H1.2 App C No-Go Zones 2
H1.3 DRG CC 002 New site layout
H1.4 DRG CC 0003 New site layout

Appendix I: Screening Tool Report

I.0 Screening tool report
I.1 Screening tool

Appendix J: Impact & Risk Assessment

The Impact and Risk Assessment Alternative

Appendix K: Environmental Management Guideline

Need and Desirability Report

Appendix L: Existing EA, DEA&DP Communication and Pre-application meeting record

Existing EA, DEA&DP Communication and Pre-application meeting Record

L.1: DEA & DP checklist

L.2: Pre-app Meeting Record

L.3: Macassar EA

Appendix M: Site Sensitivity Verification Report

Macassar Site Sensitivity Verification Report.

Appendix N: Footprint Comparisons

Motivational comparison Revised upgrade design and authorised upgrade

Appendix O: Climate Change

Climate Change Statement

Appendix P: Final Basic Assessment Report (BAR)

P.1 Final Basic Assessment Application Declaration
P.2 Declaration of the EAP
P.3 STS B Bleuler
P.4 ASHA Consulting
P.5 Blu Science
P.6 Dr Boucher
P.7 Graham Avery
P.8 Nicke Helme Botanical Surveys
P.9 SoilZA (Johann Lanz)
P.10 STS C Lamb
P.11 STS – S van Staden
P.12 STS SL Daniels
P.13 STS Corlie Steyn CV

Appendix Q: Property sizes for all sites

Property sizes for all sites

REGISTRATION AND COMMENTS:

contact-us